Redevelopment building works blog
Mon 21 Sept
The new floor is now finished!


--------------------
Wed 5 August
Delivery and fitting of the glass for the new lightbox. A very exciting day at Chapter!
![lightbox 026 []](/resource/16967.25303.file.eng.jpg)






--------------------
Fri 10 July
Things are really starting to take shape behind the hoardings. The new Bar is now in situ...

and it goes on...

and on...

The extension on the extension:

The new improved Gallery space:

One of our friendly builders putting the finishing touches to the front entrance:

--------------------
Tue 7 July
The new theatre Fire Escape arrives:

--------------------
Tue 9 June
The new and improved car park is now open. Here's a little glimpse of what you'll see on your next visit and a view through what will be the new north entrance.


--------------------
Mon 1 June
The machine to lay the new tarmac in the carpark has arrived.

--------------------
Tue 19 May
Box Office, Marketing and Fundraising staff get hard-hatted up to explore the building site.

The concourse (looking towards the front of the building) waiting for new doors and floor.

Laying the floor for the new Box Office.

The new café bar extension.

Looking up through where the new skylight will be.

--------------------
Thu 14 May
Our new theatre seats, under wraps and safely protected from the dust.

--------------------
Fri 3 April
The new roof on the cafe extension.


--------------------
Wed 18 March
The "Finnboard" roof joists for the new bar extension are being installed today.

--------------------
Fri 13 March
Another sneak peek at how things are progressing behind the hoardings.






--------------------
Thu 26 Feb
Installation of the steel joists in the new caffi/bar and north entrance area.





--------------------
Wed 25 Feb
Lots of lorries - the new Caffi Bar steel beams being delivered and crane arriving.



--------------------
Tue 3 Feb
A little bit of weather...

--------------------
Fri 30 Jan
Inside the new Cinema 2...

--------------------
Thu 22 Jan
This is the temporary 'Haki' fire escape, which has been erected to replace the old theatre fire escape which is being demolished today.

--------------------
Fri 2 JanHere are some more pictures of the temporary supports (needling) in Unit 68 & the supports in the rear court yard prior to Theatre structural beams being installed.




--------------------
Wed 17 Dec
These pictures show the "needle supports" inside the Theatre and outside by the old fire escape. These are to support the building prior to new steel beams being installed.


--------------------
Tue 16 Dec
On Friday, we had a visit from another crane which was lifting in steel beams which will eventually form part of the support in the Gallery area.



--------------------
Fri 5 Dec
This a photo of the steel beams that, when installed, will support the walls & floor above the new Box office.

--------------------
Mon 1 Dec
Today scaffolding has been erected in the area of the temporary entrance.

--------------------
Wed 19 Nov
This is the rear courtyard alongside the original Cafe wash up & prep area. The large, fenced off hole is being prepared for concrete to be poured in to support the steel framework which will form part of the new Bar/Cafe area.

--------------------
Mon 17 Nov
Our new boiler room is now completed and the heating has been turned on!

--------------------
Thu 23 Oct
Today WRW are breaking through the wall between the Cinema 2 projection room and the Cinema 2 auditorium to make the opening for the steel supports for the "super porthole", through which films will be projected. The picture shows the steel props holding the wall up prior to the brickwork being removed and the steel beam being installed in Cinema 2.

--------------------
Fri 17 Oct
Builders at work. Wheelbarrows essential...


--------------------
Mon 13 Oct
Up on a roof...


--------------------
Mon 29 Sept
The new entrance from the car park into the new patio area is opening up!


--------------------
Fri 18 Sept
Here's a sneaky peek at how things are coming along in the new foyer area...



--------------------
Thu 11 Sept
The work on Cinema 2 is cracking on at an astonishing pace. Here's a look at how the builders are getting on - rest assured it will look much brighter and more comfortable come the reopening in November!



--------------------
Tue 12 Aug
The building work is well on its way behind the hoardings. This week, the seats are being removed from Cinema 2 and walls will start to come down. Here's a look at what's been done so far in the old cafe/bar area...




--------------------
Mon 14 July
Our new Caffi Bar Chapter is settling well into its new home. If you haven't popped in already here's a little taster of what you can expect when you get here. It may be in a new location but it still has that unmistakable Chapter atmospere.





--------------------
Thu 10 July
Here's a sneak peek at what the builders have been up to in those hard to reach areas...



--------------------
Fri 4 July
It's been a little while since we've updated you about how things are going so here's a whistle-stop tour of what we've been up to in the last few weeks, readying ourselves for the opening of Caffi Bar Chapter in its temporary home and the start of the big building works in the main building. There'll be more on what the builders are up to in those parts of the building we're no longer allowed in in the next couple of weeks...
Installing the new field kitchen



Bidding a fond 'farewell' to the old Box Office

Moving the cafe to its new home


Back open and business as usual



--------------------
Mon 28 April

TRACT have finished their work for now. The Stiwdio is taking shape in readiness for changeover in June, when work will begin on the main Chapter building.
We have cleared out the new keg stall under the Stiwdio steps. The new bar is being constructed as we speak.
The new Annexe (Stiwdio attic) fire escape is ready and performances and exhibitions have begun within.
Temporary bin storage has been sorted out.
We’ve added a fire alarm repeater panel to the Stiwdio doors. Brand new locks and alarms have been installed and escape route lighting is nearly ready.
The temporary Site office is being knocked into shape.
And the temporary Box Office/Gallery Shop space is being cleared out and prepared for phone and computer wiring.
Full steam ahead…
--------------------
Fri 28 March

Today TRACT will be installing the canopies at the Stiwdio entrance and at the covered walkway behind the "field kitchen" which will be installed in the Stiwdio compound. The final carpentry is also being carried out today. Decoration continues.
--------------------
Wed 26 March

The ramp to get the beer barrels into the Stiwdio bar has been erected. Carpentry work continues on the new doors that are part of the enabling works. The temporary Box office and Gallery shop is being painted today.
--------------------
Tue 25 March

The Stiwdio annexe electrics are finished. The coded door at the entrance to Ffotogallery workshops is being "swung round" today so as to allow access to the new temporary Box Office & Gallery shop. Decoration work continues.
--------------------
Thu 20 March

The staircase is now installed. Fire proof cladding is being installed in that area to protect the staircase in emergencies. New doors are being installed @ SWAS ground floor fire exit, the fire exit opposite Morgan Hall’s studio & the new Facilities office.
Inside the Stiwdio has been painted white. The hoarding boards have been coated with a clear sealant. Decoration continues on the rest of the project.
--------------------
Wed 19 March
Here's a sneak peek at how things are coming along inside the STIWDIO...



--------------------
Mon 10 March

Today TRACT are overseeing the removal of the scaffolding at the east side of the Stiwdio. The staircase is also being worked on.
Also, today work starts on installing a Fire Alarm repeater panel for the refurbishment works. This involves installing a cable from the existing fire panel to a position by the new main building temporary entrance, i.e. opposite Morgan Hall's studio.
--------------------
Mon 3 March

Today TRACT will start putting up the hording boards. Cordless drills & hammers will be used.
Unit 8 is all but finished & painting of that area will start this week.
The bar glass washing area is also ready to be decorated.
The installation of the staircase between the Stiwdio annexe & the Stiwdio is planned to be started on Friday 7th March.
--------------------
Fri 29 Feb

Today TRACT will be drilling by the Stiwdio in preparation for the cover to be installed over the ramped entrance. They will also be finishing the carpentry in unit 8.
--------------------
Tue 26 Feb

TRACT will be installing the new doors in the Stiwdio today.
--------------------
Mon 25 Feb

TRACT will continue working on the Stiwdio opening from the annexe to the Stiwdio control room & work will proceed on the partitioning of unit 8.
--------------------
Thu 21 Feb

TRACT will continue with the Stiwdio enabling works.
Nothing major to report.
--------------------
Wed 20 Feb

Today TRACT are having a large delivery of plasterboard to continue partitioning unit 8.
--------------------
Tue 19 Feb

Today TRACT will continue erecting partition walls in the Stiwdio & unit 8.
Scaffolders will also be on site working on the Llandaff Rd side of the Stiwdio.
--------------------
Mon 18 Feb

Tract site manager reports everything OK – no problems.
--------------------
Fri 15 Feb

Today TRACT will be erecting scaffolding at the Llandaff Rd side of the Stiwdio in our neighbours gardens. Mosem & I have visited the houses in Llandaff rd to inform the neighbours that this is happening today.
They will also be working on the opening for the new staircase inside the Stiwdio.
Electricians will continue work in unit 8 the Stiwdio & the Cinemas corridor.
--------------------
Thu 14 Feb

Today TRACT will be laying down concrete for the ramp in the new facilities office at the rear of Chapter. There will be a concrete mixer lorry arriving at 08.00 ish. I will ask TRACT to try and keep the noise down @ the frontage after lunch as the Decorative and Fine Arts Society are here this afternoon, so the 2.30 film will have to be in Cinema 2.
--------------------
Wed 13 Feb

Today TRACT will be mainly working in the Stiwdio making the opening for the new staircase. They will also be continuing work on the new doorways into Pete Williams old studio [unit 8] & the new Facilities office [unit 12] . Electricians are also on site working in unit 8 & the Stiwdio.
--------------------
Mon 11 Feb

Much the same as last week in the front car park also Trac will be starting to build platform between stiwdio and the main building and preparing the area for the ramp into the site office
--------------------
Fri 8 Feb

work in the car park, making things ready for the portable toilets continues today we have plumbers in starting to remove radiators in units 8 and 12
contractors still removing asbestos chimney
|